Construction update – January 2014

It is good to report that construction of The Hive is still on schedule for our opening in May 2014, despite the recent poor weather.

The work has hit plenty of milestones recently, including all of the glazing being installed, solar panels lifted on to the roof and scaffolding has been removed from the northern face of the building. Milestones still to come include; the removal of the rest of the scaffolding, addition of the spiral fire escape stairways and finishing off the internal partitions (which are also removable).

Here’s a small gallery of the latest images to give a flavour of all of the building activity going on – it really is buzzing!